Scope Of Work
                                    Mechanical, production, construction and manufacturing erection/installation works of the Woodworking Plant of Yıldız Sunta A.Ş. and that has 1500 m³ / day capacity, were carried out by our company.
                                     
                            - 2.170 ton Steel Construction Manufacturing Erection
 
- Sand Blasting, Painting Operations of 1.250 ton Steel Construction System and 14.500 m Pipe Manufacturing Installation
 
- 29.400 m² Insulation 
 
- Production and Assembly of 410 ton Cyclone and Pneumatic Lines and 75 ton-Capacity Stainless Tank Manufacturing Installation/Erection
 
- Rotary Dryer Manufacturing Installation / Erection(Ø:6m, L: 32m)
 
- 350 tons-Capacity 6 pcs Water Tank
 
- 200 tons-Capacity Water Tank